help • 12 Devices • DECT telephones • Provisioning the DCF DECT system • Activating the DECT 600 system
12.3.1.7 Activating the DECT 600 system
To activate a new DECT system and put all assigned DECT end devices into operation, you must first connect only one DECT 600 base station to your network.
This base station is automatically configured as the master and provided with the current firmware and SwyxWare configuration.
Requirements:
*DECT hardware is prepared for deployment, see 12.3.1.2 Prepare DECT 600 hardware.
*DECT system objects (including base stations and handsets) have been created, see 12.3.1.3 Creating a DECT system
To activate a DECT 600 system via DCF
The master base station is connected to the network and switched on.
1 Restart the base station.
*The SwyxWare configuration is uploaded. The LED on the base station lights up green continuously.
2 In the Swyx Control Center, open Devices | DECT | DECT Base Stations | Firmware version and check the status of the current firmware.
3 You can now connect additional DECT 600 base stations to the network.
*The base stations are automatically recognized and set up.
* 
The password for access to the administration interface of the base stations is changed during provisioning.
The default password must be used to access the DCF system. This can be found under General settings | System | Provisioning | Administrative device password for certified phones.
 
* 
Configurations made in the WebUI are not saved on the SwyxServer and must be carried out again after a factory reset and subsequent re-provisioning.
Configuration that is provisioned is overwritten with each provisioning. (e.g. LDAP configuration)